Risks, Issues & Change Requests User Guide

This guide explains how to track and manage Risks, Issues, and Change Requests (RIC) in Agilebars, Timebars, and Costbars applications. The RIC system helps you identify potential problems, log current issues, and manage proposed changes—all directly on your project timeline.

Table of Contents

  1. Overview: What is the RIC System?
  2. Quick Start: Creating Your First RIC Item
  3. Visual Indicators on the Canvas
  4. Accessing the RIC Management Page
  5. Card View: Visual Management
  6. Tabular View: Data Analysis
  7. Search and Filter
  8. Editing with FOCD Forms
  9. Managing Risks
  10. Managing Issues
  11. Managing Change Requests
  12. Customizing Forms and Picklists
  13. Tips and Best Practices
  14. Troubleshooting
  15. Data Storage
  16. Related Help Topics
  17. Summary

Overview: What is the RIC System?

The RIC (Risks, Issues, Change Requests) system allows you to:

  • Track Risks: Potential problems that might occur in the future
  • Manage Issues: Problems that are happening right now
  • Handle Change Requests: Proposed changes to project scope, schedule, or budget

Key Concepts:

  • RIC items are created as regular tasks using the Bar Creator
  • Each item is classified by changing the SubType field (Risk, Issue, or CR)
  • Visual indicators appear automatically on the Canvas (R, I, or CR prefix)
  • Dedicated views provide filtering, searching, and detailed tracking
  • Customize forms to match your organization's methodology

Quick Start: Creating Your First RIC Item

Step-by-Step Creation

  1. Create a Task Bar:

    • Click Main Menu > New Bar
    • Drag the Task Creator Bar (blue) onto a Project Bar (green)
    • Drop to create the task
  2. Open the Form:

    • Click on the bar name to open the Slide Out Right Form
  3. Change Name:

    • Update the task name to describe your Risk, Issue, or CR
    • Examples:
      • "R-Database Migration Failure Risk"
      • "I-Server Outage on Production"
      • "CR-Add Mobile App Support"
  4. Set SubType:

    • Find the SubType field in the form
    • Change from "Task" to "Risk", "Issue", or "CR"
  5. Visual Indicator Appears:

    • Risk: Bold R prefix appears before bar name
    • Issue: Bold I prefix appears before bar name
    • Change Request: Bold CR prefix appears before bar name
  6. Save and Close:

    • Data saves automatically
    • Close the form

That's it! You've created a RIC item. Now let's explore how to track and manage it.


Visual Indicators on the Canvas

RIC items display with automatic visual indicators to help you quickly identify them:

Prefix Letters

  • R = Risk
  • I = Issue
  • CR = Change Request

Color Coding by Status

When you set the Status field to specific values, the visual indicator changes:

Status Visual Effect When to Use
Normal Black bold letter Standard priority
Concerned Red letter with thin red border Needs attention
Critical RED letter with thick red border Urgent action required

Example:

  • Normal Risk: R Database Migration Failure (black)
  • Concerned Issue: I Server Outage on Production (red letter, thin border)
  • Critical Risk: R Security Vulnerability Discovered (red letter, thick border)

Accessing the RIC Management Page

To view and manage all your Risks, Issues, and Change Requests in one place:

  1. Choose Main Menu > RIC (or Main Menu > Risks/Issues)
  2. The RIC page opens with Card View as the default

Two View Options:

  • Card View: Visual cards with expandable details (recommended for viewing)
  • Tabular View: Sortable table with all fields (recommended for bulk analysis)

Card View: Visual Management

Card View displays your RIC items as color-coded, expandable cards in a two-column responsive grid.

Card Colors by Type

  • Risk Cards: Blue gradient background
  • Issue Cards: Red gradient background
  • Change Request Cards: Pink/Purple gradient background

Card Structure

Each card shows:

1. Header Section:

  • Breadcrumb: Project hierarchy (Portfolio > Program > Project)
  • SubType Chip: Colored badge (Risk/Issue/CR)
  • ID and Name: Item identifier and title
  • Action Buttons:
    • Edit (pencil icon) - Opens full FOCD form
    • Print (printer icon) - Prints this card

2. Metadata Section (Always visible):

  • Parent Project: Which project this belongs to
  • Dates: Start/Finish (planned) and Actual dates (if started/completed)
  • Schedule Health: Color-coded indicator (Green/Yellow/Red)
  • Risk-Specific:
    • Probability: Likelihood rating
    • Impact: Severity rating
    • Score: Auto-calculated (Probability × Impact) with color coding
    • Mitigation Status: Current mitigation progress
  • Escalation Level: Color-coded (e.g., red for Executives)
  • Owner: Person responsible
  • Status: Current status (New, In Progress, Closed, etc.)
  • State: Workflow state (Awaiting Approval, Approved, etc.)
  • Category: Classification type
  • Priority: Color-coded (Immediate, High, Normal, Low)

3. Details Section (Expandable - Click "Show Details"):

For Risks:

  • Description
  • Executive Summary
  • Notes
  • Risk Response Strategy (rich text)
  • Mitigation Plan (rich text)
  • Contingency Plan (rich text)

For Issues:

  • Description
  • Executive Summary
  • Notes

For Change Requests:

  • Tabbed Interface with 4 tabs:
    • Overview: Description, Executive Summary, Problem/Opportunity
    • Impact Assessment: Schedule, Budget, Scope, Resource Commentary
    • Benefits & Justification: Expected Benefits, Cost-Benefit Analysis, Options Analysis
    • Notes: Implementation Approach, Next Steps, Dependencies

Inline Editing in Cards

You can edit text fields directly in the cards:

  1. Click "Show Details" to expand the card
  2. Click on any text field
  3. Edit the content
  4. Click outside the field to save automatically
  5. Rich text editors available for Risk strategy/plan fields

Note: Some fields require opening the full FOCD form to edit.


Tabular View: Data Analysis

Tabular View displays all RIC items in a sortable, scrollable table—ideal for analysis and reporting.

Features

  • Sortable Columns: Click any column header to sort ascending/descending
  • Fixed Actions Column: Edit button always visible on the left
  • Horizontal Scrolling: Scroll right to see all columns
  • Compact View: See many items at once
  • Quick Access: Click Edit button to open FOCD form

Available Columns

The table includes columns for:

  • Actions (Edit button)
  • Hierarchy (L1, L2, L3)
  • ID, Name, SubType
  • Start Date, Finish Date, Actual Start, Actual Finish
  • Owner, Status, State, Priority
  • Risk Fields: Probability, Impact, Score, Category, Mitigation Status, Escalation Level
  • Health Indicators: Schedule Health (color-coded)
  • Description, Executive Summary, Notes

Sorting Data

  1. Click any column header (e.g., "Priority")
  2. Data sorts ascending
  3. Click again to sort descending
  4. Default sort: Hierarchy Order (top to bottom as on Canvas)

Search and Filter

Both Card View and Tabular View include powerful search and filter tools at the top of the page.

Search Box (top of page):

  • Type any text to search across all fields
  • Results filter in real-time as you type
  • Searches: Names, Descriptions, Notes, all text content

Example:

  • Type "database" to find all items mentioning database
  • Type "migration" to find migration-related items

Picklist Filters

Filter Dropdowns:

  • Multiple dropdown filters available
  • Filter by any picklist field:
    • SubType: Show only Risks, Issues, or CRs
    • Status: Active, Closed, On Hold, etc.
    • Priority: Immediate, High, Normal, Low
    • Owner: Filter by responsible person
    • Category: Filter by classification
    • Escalation Level: Show only escalated items
    • State: Filter by workflow state

Combining Filters:

  • Select multiple filters to narrow results
  • Example: Show only "High Priority Risks" with "Critical Status"

Recalculate All Button

Click "Recalculate All" to:

  • Refresh all calculated fields
  • Recalculate every Risk Score from its current Probability and Impact (use this after any change to those picklists, and to clear scores left over from the old 0-100 scale)
  • Ensure data consistency across views
  • Rebuild system-generated data

Editing with FOCD Forms

FOCD (Field-Oriented Control Design) forms provide detailed editing of all RIC metadata.

Opening a FOCD Form

Three Ways to Open:

  1. Click Edit button (pencil icon) on any card
  2. Click Edit button in Tabular View row
  3. Click on a bar on the Canvas, then click Edit in the popup

Two Form Types:

  • Risk Edit Form (dfRisk): For Risks and Change Requests
  • Issue Edit Form (dfIssue): For Issues

Form Features

Auto-Save:

  • Changes save automatically to the database when you move off a field
  • No "Save" button needed for most edits

Rich Text Editors (Risks Only): Three fields use rich text editors:

  • Risk Response Strategy: Formatted text with bold, italic, lists
  • Mitigation Plan: Detailed action plans with formatting
  • Contingency Plan: Backup plans with formatting

Risk Score Calculator:

  • When you change Probability or Impact, the Score field updates automatically
  • Formula: Score = Probability (1-5) x Impact (1-5) = 1 to 25, higher is worse

Field Types:

  • Text Inputs: Standard single-line text
  • Dropdowns: Picklist selections
  • Text Areas: Multi-line text with auto-resize
  • Rich Editors: Formatted text (Risks only)
  • Date Pickers: Calendar date selection
  • Section Headers: Organize fields into groups

Form Actions

Save Button:

  • Click to explicitly save all changes
  • Returns to Card or Tabular View

Move/Resize Fields Button:

  • Click to enter customization mode
  • Drag fields to reposition
  • Resize using edge handles
  • Click "Stop" to save layout

Close Button (X):

  • Saves changes and closes form
  • Reloads application with updated data

Managing Risks

Risks are potential problems that might occur in the future. Effective risk management helps you prevent issues before they happen.

Core Risk Fields

When managing a Risk, you'll work with these key fields:

1. Probability (Likelihood)

How likely is this risk to occur? Each value carries a weight of 1 to 5, used to calculate the Score:

Value Weight
Very Unlikely 1
Unlikely 2
Likely 3
Very Likely 4
Certain 5
Not Assessed no weight — the risk scores 0

Do not rename these five values. The weights are held in the application code and matched by exact text, so a renamed value stops scoring altogether and the risk silently reads Not Assessed. You may add values, but only these five produce a score. See Customizing picklists below.


2. Impact (Severity)

How severe would the consequences be if this risk occurs? Consider schedule, budget, scope and quality. Each value carries a weight of 1 to 5:

Value Weight
Very Low 1
Low 2
Medium 3
High 4
Very High 5
Not Assessed no weight — the risk scores 0

The same warning applies: these five values are matched by exact text and must not be renamed.


3. Score (Auto-Calculated)

The Score follows the standard 5x5 probability-impact matrix used by PMBOK, ISO 31000, PRINCE2 and M_o_R:

Score = Probability (1-5) x Impact (1-5) → 1 to 25, where higher is worse.

It is calculated for you the moment you set both axes, on every surface — the risk form, the cards, the tabular view and the inline grid.

Set only one axis and the score stays 0. So does setting either to Not Assessed. A score of 0 means not assessed, and is deliberately outside the valid 1-25 range so it can never be mistaken for a real, low assessment.

The four bands:

Band Score Reading
Low 1-4 green
Moderate 5-9 amber
High 10-14 orange
Extreme 15-25 red
Not Assessed 0 grey

The score displays as the number and its band together — 12 - High — so the reading never depends on remembering where the boundaries fall.

Worked examples:

Probability Impact Score Band
Certain Very High 25 Extreme
Likely High 12 High
Unlikely Medium 6 Moderate
Very Unlikely Very Low 1 Low
Likely (not set) 0 Not Assessed
The risk matrix panel

The risk form carries a 5x5 heat map showing all 25 combinations, with your assessed cell ringed. Probability runs down the rows worst-first and Impact across the columns, so it reads like any published risk heat map. Hovering a cell tells you its combination, score and band, and a legend underneath shows the four band ranges.

The panel is draggable — move it aside if it covers a field you are working on.

A note if you have used earlier versions. The score used to run the other way: it was normalised to 0-100 and inverted, so 100 meant safest. Most of the product read it as higher-is-worse, which meant the safest risk on a card rendered in the loudest red and the most dangerous one in plain small text. The scale, the colours and the matrix now all run the same direction. Scores recorded under the old scale are meaningless on the new one — reassess, or run Recalculate All, which recalculates every score from its Probability and Impact.


4. Category

Classify the type of risk:

Default Values for Risks:

  • Strategic: Alignment with business goals
  • Financial: Budget and funding risks
  • Operational: Day-to-day operations
  • Technical: Technology and system risks
  • Organizational: People and structure risks

5. Risk Response Strategy

Your written approach to handling the risk.

Common Strategies:

  • Avoid: Change plans to eliminate the risk
  • Mitigate: Reduce likelihood or impact
  • Transfer: Shift risk to third party (insurance, vendor)
  • Accept: Acknowledge risk and prepare to deal with it

Field Type: Rich text editor (supports formatting)


6. Mitigation Plan

Detailed actions to reduce the risk.

What to Include:

  • Specific steps to take
  • Who is responsible for each step
  • Timeline for completion
  • Resources needed
  • Success metrics

Field Type: Rich text editor (supports formatting)


7. Mitigation Status

Track progress of your mitigation efforts.

Default Values:

  • Identified: Risk recognized but not yet assessed
  • Assessed: Analysis complete
  • Mitigation Planned: Plan created
  • In Progress: Executing mitigation
  • Mitigated: Risk reduced to acceptable level
  • Under Review: Evaluating effectiveness
  • Accepted: Acknowledged without mitigation
  • Transferred: Shifted to third party
  • Escalated: Raised to higher management
  • Closed: Risk no longer relevant
  • Deferred: Postponed to later

8. Contingency Plan

Backup plan if the risk occurs despite mitigation.

What to Include:

  • Fallback actions
  • Resources reserved for response
  • Decision triggers
  • Communication plan

Field Type: Rich text editor (supports formatting)


9. Escalation Level

Who needs to be informed if this risk materializes?

Default Values:

  • Executives: C-level notification
  • Directors: Department heads
  • Project Office: PMO oversight
  • Not Assessed

Display: Color-coded based on level


10. Trigger Event

What event or condition signals this risk is occurring?

Examples:

  • "Server CPU usage exceeds 80% for 24 hours"
  • "Project spend reaches 90% of budget with 40% work remaining"
  • "Key vendor misses two consecutive delivery dates"

Field Type: Plain text area


11. Early Warning Indicators

Metrics or signals to detect the risk early.

Examples:

  • Weekly defect trend increasing
  • Resource availability dropping below threshold
  • Velocity declining for two sprints
  • Stakeholder engagement score decreasing

Field Type: Plain text area


Risk Management Workflow

Step 1: Identify

  1. Create Risk item on Canvas (SubType = Risk)
  2. Give it a clear, descriptive name
  3. Set Category for classification

Step 2: Assess

  1. Open RIC page (Main Menu > RIC)
  2. Find your risk and click Edit
  3. Set Probability and Impact
  4. Review calculated Score
  5. Set Escalation Level if needed

Step 3: Plan Response

  1. Write Risk Response Strategy (Avoid/Mitigate/Transfer/Accept)
  2. Detail Mitigation Plan with specific actions
  3. Write Contingency Plan as backup
  4. Set Trigger Event and Early Warning Indicators
  5. Assign Owner
  6. Set Mitigation Status to "Mitigation Planned"

Step 4: Execute Mitigation

  1. Update Mitigation Status to "In Progress"
  2. Add progress Notes regularly
  3. Monitor early warning indicators
  4. Update Status to "Concerned" or "Critical" if risk increases

Step 5: Monitor and Close

  1. Review risk regularly (weekly/monthly)
  2. Update Probability/Impact if conditions change
  3. When risk is addressed:
    • Set Mitigation Status to "Mitigated" or "Closed"
    • Set Status to "Closed"
    • Document outcome in Notes

Managing Issues

Issues are problems that are happening right now and require immediate attention.

Core Issue Fields

Issues use simpler fields than Risks since the problem has already occurred:

Key Fields:

  • Description: What is the problem?
  • Executive Summary: High-level summary for management
  • Notes: Updates on resolution progress
  • Status: Current state (New, In Progress, Closed, etc.)
  • State: Workflow tracking (Awaiting Input, Under Review, etc.)
  • Priority: Urgency level (Immediate, High, Normal, Low)
  • Owner: Person responsible for resolving
  • Escalation Level: Who needs to know (Executives, Directors, Project Office)
  • Category: Type of issue

Category Values for Issues:

  • Product: Product defects or problems
  • Financial: Budget or cost issues
  • Operational: Process or operational problems
  • Technical: Technical failures or bugs
  • Schedule: Timeline delays

Issue Management Workflow

Step 1: Log the Issue

  1. Create Issue item on Canvas (SubType = Issue)
  2. Give it a clear name describing the problem
  3. Set Priority based on urgency
  4. Set Category for classification

Step 2: Assess

  1. Open RIC page and click Edit
  2. Write detailed Description of the problem
  3. Write Executive Summary for stakeholders
  4. Set Escalation Level if critical
  5. Assign Owner to resolve

Step 3: Resolve

  1. Update Status to "In Progress"
  2. If urgent: Set Status to "Concerned" or "Critical" (triggers red visual indicator)
  3. Add Notes with resolution activities
  4. Update State as it moves through workflow (e.g., "Awaiting Approval")

Step 4: Close

  1. When resolved:
    • Set Status to "Closed"
    • Document resolution in Notes
    • Set Actual Finish date
  2. Review Notes to capture lessons learned

Managing Change Requests

Change Requests (CRs) track proposed changes to project scope, schedule, budget, or resources.

Core CR Fields

CRs have extensive fields to justify and analyze the proposed change:

Overview Tab:

  • Description: What is the change?
  • Executive Summary: High-level summary
  • Problem/Opportunity: What drives this change?

Impact Assessment Tab:

  • Schedule Commentary: How does this affect timeline?
  • Budget Commentary: Cost impact
  • Scope Commentary: How does scope change?
  • Resource Commentary: Resource needs

Benefits & Justification Tab:

  • Expected Benefits: What do we gain? (Rich text editor)
  • Cost-Benefit Analysis: Is it worth the investment?
  • Options Analysis: What alternatives were considered?

Notes Tab:

  • Implementation Approach: How will we execute?
  • Next Steps: Immediate actions
  • Key Dependencies: What's needed to proceed?

Common Fields:

  • Owner: CR sponsor/requestor
  • Status: Approval status
  • State: Workflow state (Awaiting Approval, Approved, etc.)
  • Priority: Importance level

Change Request Workflow

Step 1: Submit CR

  1. Create CR item (SubType = CR)
  2. Name it clearly (e.g., "CR-Add Mobile App Support")
  3. Open RIC page, find CR, click Edit

Step 2: Document Justification

  1. Overview Tab:
    • Write detailed Description
    • Write Executive Summary
    • Explain Problem/Opportunity
  2. Benefits Tab:
    • Document Expected Benefits (use rich text formatting)
    • Complete Cost-Benefit Analysis
    • Describe Options Analysis (alternatives considered)

Step 3: Assess Impact

  1. Impact Assessment Tab:
    • Schedule Commentary: Add X weeks? Delay milestone?
    • Budget Commentary: Cost increase? Source of funds?
    • Scope Commentary: What's added/removed?
    • Resource Commentary: Need additional people/skills?

Step 4: Plan Implementation

  1. Notes Tab:
    • Implementation Approach: How will we execute?
    • Key Dependencies: What must happen first?
    • Next Steps: Immediate actions
  2. Set Owner (requestor)
  3. Set Priority

Step 5: Approval Process

  1. Set State to "Requested Approval"
  2. Update Status and State as it moves through workflow:
    • Awaiting Approval
    • Approved / Rejected
    • Awaiting Implementation
  3. Add Notes with decision rationale

Step 6: Implementation or Closure

  • If Approved: Create tasks to implement, link to CR
  • If Rejected: Set Status to "Rejected", document reason
  • If Complete: Set Status to "Closed"

Customizing Forms and Picklists

The Risk and Issue forms, and every picklist behind them, are configured the same way as everything else in the product. The Forms, Reports and Graphs Guide is the full reference; this section covers only what is specific to Risks, Issues and CRs.

Earlier versions of this guide routed you through Reports > Data Management Grids. That screen no longer exists. Configuration now lives on five reports under Report Menu > Other.

Show, hide, move and add fields

Report Menu > Other > Fields Values. Filter the Form column to dfRisk or dfIssue and you have every field on that form, one per row.

To do this Do this
Hide a field open it on the form and set Show to No
Show it again set Show back to Yes
Reposition or resize edit Top, Left and Width directly in the grid
Add a field filter to the form first, click Add, then pick the field name
Remove a field delete its row

The layout columns are the only cells in that report you edit in the grid rather than on the form — because laying out a form means comparing one field's numbers against its neighbours'.

Or move fields by hand. Open a Risk or Issue form, click the Move/Resize Fields button, drag the fields where you want them, and click Stop to save. Easier than typing coordinates for small adjustments.

Which picklists drive Risks, Issues and CRs

Report Menu > Other > Picklist Values. Filter to the picklist, open a value, edit it.

Picklist Field Notes
Risk Probability tbMDProbability Do not rename the five scoring values — see below
Risk Impact tbMDImpact Do not rename the five scoring values
Risk Category tbMDCategory free to customise; add your own
Issue Category tbMDCategory free to customise
CR Category tbMDCategory free to customise
Mitigation Status tbMDMitigationStatus free to customise, with one exception: Escalated is read by the health rules
Escalation Level tbMDEscalationLevel Executives, Directors, Project Office are read by the health rules
Timebar Status tbMDStatus Closed and Rejected are what make an item stop counting
Approval State tbMDState the workflow states
Timebar Priority tbMDPriority free to customise
RandIStage, RandIState, RandIStatus R&I workflow free to customise

Values in bold are locked. They carry a padlock in Picklist Values and cannot be renamed there, because the application compares against that exact text. You may always add your own values to any of these lists.

Why the locked values matter here specifically

Risks, Issues and Change Requests do not just describe themselves — they drive their parent project's Scope, Risk and Issue health indicators. Those rules read your items by exact value:

  • An item stops counting toward health once its Status is Closed or Rejected.
  • An open item escalated to Executives or Directors, or a risk whose Mitigation Status is Escalated, turns the parent's indicator Red.
  • An open item escalated to Project Office, or three or more open items, turns it Yellow.

Rename one of those values and the health rules stop seeing your escalations — without any error. The Forms, Reports and Graphs Guide covers the full rule set.

People fields come from the Resource Pool

Contact / Requestor, and the other person-named fields on these forms, no longer read a picklist of typed names. They read the live Resource Pool — the Human rows in Resources. To change who can be picked, maintain the resource pool, not the Tags table.


Tips and Best Practices

Risk Management

  1. Regular Reviews: Review risks weekly or bi-weekly
  2. Update Probability/Impact: Reassess as conditions change
  3. Monitor Early Warnings: Track indicators proactively
  4. Document Triggers: Define clear conditions that signal risk is occurring
  5. Keep Plans Current: Update mitigation plans as you learn more
  6. Use Visual Indicators: Set Status to "Concerned" or "Critical" for urgent risks

Issue Management

  1. Log Immediately: Create issues as soon as problems occur
  2. Escalate Appropriately: Set Escalation Level for critical issues
  3. Update Progress: Add Notes regularly with resolution activities
  4. Set Clear Ownership: Always assign an Owner
  5. Close Properly: Document resolution and lessons learned
  6. Use Red Indicators: Set Status to "Critical" for urgent issues to trigger visual alerts

Change Request Management

  1. Complete Justification: Fill all Impact Assessment fields
  2. Quantify Benefits: Use specific metrics in Expected Benefits
  3. Consider Alternatives: Document Options Analysis thoroughly
  4. Track Through Workflow: Update State as approval progresses
  5. Link to Implementation: Create implementation tasks and link to CR

General Best Practices

  1. Consistent Naming: Use prefixes (R-, I-, CR-) in names
  2. Use Categories: Classify items for better filtering
  3. Set Priorities: Helps sort and filter critical items
  4. Leverage Search: Use search box to find items quickly
  5. Print Cards: Print individual cards for meetings or reviews
  6. Regular Recalculation: Click "Recalculate All" periodically to ensure data accuracy
  7. Customize Forms: Remove unused fields to simplify forms
  8. Standardize Picklists: Ensure team uses consistent terminology

Troubleshooting

Visual Indicator Not Appearing

Problem: R, I, or CR prefix doesn't show on Canvas

Solution:

  1. Verify SubType field is set to "Risk", "Issue", or "CR" (exact spelling)
  2. Refresh Canvas (click Refresh icon on top menu)
  3. If still missing, Right-click Canvas > Recalculate All

Status Not Turning Red

Problem: Set Status to "Concerned" but letter doesn't turn red

Solution:

  1. Ensure exact spelling: "Concerned" or "Critical"
  2. Check tbTags store has these values defined
  3. Refresh Canvas after changing Status

Risk Score Not Calculating

Cause: One axis is missing, or a value has been renamed.

Solution:

  1. Set both Probability and Impact — one alone always scores 0.
  2. Check neither is set to Not Assessed, which also scores 0.
  3. If both are set and the score is still 0, the picklist value has been renamed. The five scoring values in each list are matched by exact text: Very Unlikely, Unlikely, Likely, Very Likely, Certain and Very Low, Low, Medium, High, Very High. Restore the original spelling in Picklist Values.
  4. Run Recalculate All to recalculate every score in the database.

Cause: The score looks wrong rather than absent — a trivial risk showing red, or a severe one showing green.

Solution: The row is holding a score from the old 0-100 scale, where 100 meant safest. Run Recalculate All; every score is recalculated from its Probability and Impact on the current 1-25 scale.

Fields Missing in Form

Problem: Expected fields don't appear in Risk or Issue form

Solution:

  1. Go to Report Menu > Other > Fields Values
  2. Filter Form to dfRisk or dfIssue and find the field
  3. Open it on the form and check Show is Yes
  4. If the field has no row on that form at all, Add one and pick the field name
  5. Refresh the application after changes

Cannot Edit in Card View

Problem: Click on field in card but can't edit

Solution:

  1. Click "Show Details" to expand card first
  2. Some fields require full FOCD form—click Edit button
  3. Ensure you're not in read-only mode

Filters Not Working

Problem: Select filter but no results appear

Solution:

  1. Check that items exist with selected filter value
  2. Clear other filters—they may be combining to exclude all results
  3. Try Search box to verify items exist
  4. Click "Recalculate All" to refresh data

Data Storage

Understanding where RIC data is stored helps with backups, spreadsheet sync, and troubleshooting.

IndexedDB Stores

tbTimebars Store:

  • Contains all RIC items as task records
  • Key field: tbSubType = "Risk", "Issue", or "CR"
  • Includes: ID, Name, Type, Start/Finish dates, Hierarchy (L1-L5), Owner

tbMetaData Store:

  • Contains all metadata fields (100+ fields)
  • Links to tbTimebars via tbMDID = tbID
  • Includes: Probability, Impact, Score, Status, Priority, Description, Plans, Commentary

tbFields Store:

  • Defines FOCD form layouts
  • Contains field positions (dfCoordLeft, dfCoordTop)
  • Controls field visibility (dfShowYN)
  • Filter by dfFormName = "dfRisk" or "dfIssue"

Spreadsheet Sync

RIC items can be exported/imported via spreadsheet:

Export:

  1. Click Hamburger Icon > Export to CSV
  2. Files created: Timebars.csv and MetaData.csv
  3. Open tbClientMaster.xlsm spreadsheet
  4. Click "Import All" to load data

Edit in Spreadsheet:

  • Timebars worksheet: ID, Name, SubType, Dates, Hierarchy
  • MetaData worksheet: All 100+ metadata fields
  • Edit, add rows, copy-paste as needed

Import:

  • Save spreadsheet
  • Drag and drop onto Canvas
  • RIC items update from spreadsheet data


Summary

Key Takeaways:

  1. Three Item Types: Risks (potential problems), Issues (current problems), Change Requests (proposed changes)
  2. Create as Tasks: Use Bar Creator, then change SubType field
  3. Visual Indicators: R, I, CR prefixes appear automatically; turn red for Concerned/Critical status
  4. Two Views: Card View (visual) and Tabular View (analytical)
  5. Powerful Search: Free-text search plus multiple picklist filters
  6. FOCD Forms: Detailed editing with auto-save, rich text editors and the risk matrix panel
  7. Risk Management: Assess Probability and Impact; the Score is the 5x5 matrix product, 1-25, higher is worse
  8. Customizable: Show/hide fields, move/resize layout, customise picklists - all from Report Menu > Other
  9. Track Workflows: Use Status and State fields to track approval and resolution
  10. Regular Reviews: Update items frequently; use visual indicators for urgency

Effective RIC management helps you prevent problems, resolve issues quickly, and manage changes systematically.